SAP Certified Application Associate - Production Planning & GATP (PP/DS, GATP) in SAP SCM APO7.0 EHP2 - C_APO2_72 Sample Questions
No. Questions: 10

2 . Two production data structures (PDS) exist for a given product and are valid for the same lot size range.
PDS_A has priority 1 with a duration of 3 weeks.
PDS_B has priority 2 with a duration of 2 weeks.
Scheduling is set to backwards and reverse without negative offset. The sales order requirement date is in one week from today. A supply does NOT exist for this sales order.
What happens when you run the standard lot heuristic?


Correct Answers
  • The planned order is delayed using PDS_B as the source of supply.