The jobs should be 1 Master job (IUUC_MONITOR_SCHEMA1), 1 Master Controller job (IUUC_REPL_CNTR_001_0001) and at most 4 parallel jobs for MT_ID 001 (DTL_MT_DATA_LOAD_001_ 01/~02/~03/~04) If at the same time lots of tables are selected for load / replication, there could be a chance that there are not enough background jobs available to start the load procedure for all tables immediately. In such a case the number of initial load jobs can be increased, or else tables will be handled sequentially. For tables with large volume of data the transaction “Advanced Replication Settings (IUUC_REPL_CONT)” to further optimize the load and replication procedure for dedicated tables can be used.